NO&T Asia Legal Review
In a recent judgment dated 28 September 2021, the High Court ruled on one of the first few cases in Singapore on a commercial lease dispute arising from COVID-19 related government measures. Dathena Science Pte Ltd v Justco (Singapore) Pte Ltd [2021] SGHC 219 is a timely reminder to all that, parties’ contractual rights potentially have statutory and common law constraints, which will be enforced by the Singapore courts. Dathena Science Pte Ltd (“Dathena”), the Plaintiff in this case, had prevailed on its right to termination at common law and alternative claim under the Frustrated Contracts Act to discharge itself from a two-year lease signed with Justco (Singapore) Pte Ltd (“JustCo”).
Dathena is a cybersecurity company in the business of developing software that provides data security and privacy applications to its customers. On 16 January 2020, Dathena and JustCo (a company that provides workspaces to its customers in offices or commercial buildings that it rents) entered into a Membership Agreement whereby Dathena agreed to lease 4 units in OCBC Centre East (“OCBC Premises”), a prime location in the Central Business District area in Singapore. The lease was to run from 1 May 2020 to 30 April 2022, for a period of two years.
Due to the nature of Dathena’s business, of which JustCo was aware as Dathena had rented office space from the same JustCo’s representative at JustCo’s Bangkok office, JustCo knew that it was of paramount importance to Dathena that the OCBC Premises could meet Dathena’s information technology (“IT”) requirements and that Dathena could move its servers into the premises before the start date of the lease on 1 May 2020.
Upon the signing of the Membership Agreement, Dathena made payment of SGD 186,900 as a refundable security deposit and SGD 99,991.50 as the monthly membership fee for May 2020. Dathena also paid SGD 18,350.50 for its set up and separate housing of IT and servers within the OCBC Premises.
However, the Singapore Government implemented Circuit Breaker Measures on 7 April 2020, under the COVID-19 (Temporary Measures) (Control Orders Regulations 2020). These restrictions disrupted the IT set up that were scheduled in April 2020 and also caused delays to the construction and renovation works at the OCBC Premises. Although the Circuit Breaker Measures were originally scheduled to end on 4 May 2020, the measures were extended to 1 June 2020 as the pandemic situation remained critical in Singapore.
JustCo informed that it could not ready the OCBC Premises for Dathena in time for moving in on 1 May 2020, which was problematic for Dathena as its tenancy at its previous premises expired on the date it was supposed to move into the OCBC Premises. On 26 May 2020, JustCo expressed that it could not be certain when the OCBC Premises would be ready. On 29 May 2020, Dathena issued a Notice of Termination to discharge the Membership Agreement on either of two grounds: termination or frustration, and requested a refund of the security deposit and advanced payment of membership fees (amounting to SGD 286,891.50).
JustCo rejected Dathena’s request for a refund and denied that the Membership Agreement had been terminated or frustrated, arguing that Dathena had no contractual right to terminate the Membership Agreement, and that Dathena’s inability to commence its lease was due entirely to the mandatory circuit breaker measures imposed by the Singapore government to address the pandemic crisis. JustCo then sought to offer alternative comparable office space in lieu of the OCBC Premises as a temporary measure, citing its discretion and right to do so under the Membership Agreement.
Dathena commenced the suit against JustCo on 4 September 2020 when JustCo refused to give a refund and insisted that Dathena move into the OCBC Premises on 9 September 2020 (as it was finally ready). JustCo counterclaimed for SGD 2.4 million on the basis that it was entitled to the full membership fees it would have earned under the 2-year lease.
The Singapore High Court found in favour of Dathena on all counts, holding that:
As many businesses reconsider their template or standard terms contracts based on challenges arising from the pandemic, this judgment comes at an opportune time to highlight that parties dealing under Singapore law must bear in mind the potential constraints of Singapore statutes such as UCTA that may apply to render certain unfair terms unenforceable, especially if a commercial party is dealing on its counterparty’s standard terms of business. It is also helpful to note that even if parties have not considered possible supervening events and the consequences that should follow under a Force Majeure clause, the doctrine of frustration is nevertheless available in statute and at common law for a party looking to be discharged from its obligations under a contract. The Singapore High Court has shown that it is prepared to recognize the restrictions resulting from the COVID-19 pandemic as a supervening event that entitles a party to discharge the entire contract.
This newsletter is given as general information for reference purposes only and therefore does not constitute our firm’s legal advice. Any opinion stated in this newsletter is a personal view of the author(s) and not our firm’s official view. For any specific matter or legal issue, please do not rely on this newsletter but make sure to consult a legal adviser. We would be delighted to answer your questions, if any.
(December 2024)
Mami Ikebukuro, Kenji Utsumi, Makoto Saito, Shinichiro Horaguchi, Yoshihisa Watanabe (Co-author)
Hoai Tran
(December 2024)
Eiji Miyagi, Shiro Kato, Takahiro Kitagawa (Co-author)
Takahiro Kitagawa
Chattong Sunthorn-opas (Co-author)
(December 2021)
Shunsuke Minowa, Yothin Intaraprasong, Poonyisa Sornchangwat, Chattong Sunthorn-opas (Co-author)
Annia Hsu
Annia Hsu, Kennosuke Muro (Co-author)
(November 2024)
Oki Mori, Mai Umezawa (Co-author)
Masato Kumeuchi, Takahiro Hatori, Takayuki Inukai, Su Ai (Co-author)
(November 2024)
Kaori Sugimoto
Annia Hsu, Kennosuke Muro (Co-author)
(October 2024)
Junichi Ikeda, Tomohiko Nabeshima, Akiko Inoue (Co-author)
(July 2024)
Oki Mori, Eriko Ogata, Saki Kurachi, Natsuki Ito (Co-author)
Keiji Tonomura, Akira Komatsu, Chie Komiya, Simon Clemens Wegmann (Gleiss Lutz) (Co-author)
Annia Hsu, Kennosuke Muro (Co-author)
Salin Kongpakpaisarn, Pundaree Tanapathong (Co-author)
Hoai Tran
Axel Kuhlmann, Makoto Ohnuma, Shejal Verma (Co-author)
Annia Hsu, Kennosuke Muro (Co-author)
Salin Kongpakpaisarn, Pundaree Tanapathong (Co-author)
Hoai Tran
Luciana Fransiska
Annia Hsu, Kennosuke Muro (Co-author)
Claire Chong, Kennosuke Muro (Co-author)
Bertrice Hsu, Yuji Ibaraki (Co-author)
Kara Quek, Yuji Ibaraki (Co-author)